11/21/2025 Construction Update
-
WORK COMPLETED FOR WEEK ENDING 11/22/2025:
- Continued work on bridge deck rebar installation
- Continued work on bridge deck formwork
- Continued surcharge settlement period
-
WORK IN PROGRESS NEXT WEEK (11/23/2025 - 11/30/2025):
- Continue bridge deck rebar installation
- Continued work on bridge deck formwork
- Pour concrete bridge deck
-
UPCOMING WORK THROUGH 11/30/2025:
- Work will continue on new bridge substructure and bridge deck.
- Surcharge settlement period will be 3 months
Bridge Deck Rebar
New Bridge Looking East
Height Difference Between New and Old Bridges