11/14/2025 Construction Update

  • WORK COMPLETED FOR WEEK ENDING 11/15/2025:

    • Started work on bridge deck rebar installation
    • Continued work on bridge deck formwork
    • Continued surcharge settlement period
  • WORK IN PROGRESS NEXT WEEK (11/16/2025 - 11/22/2025):

    • Continue bridge deck rebar installation
    • Continued work on bridge deck formwork
  • UPCOMING WORK THROUGH 11/30/2025:

    • Work will continue on new bridge substructure and bridge deck.
    • Surcharge settlement period will be 3 months


Bridge deck formwork and rebar

Staging water line for future under bridge hanging