11/07/2025 Construction Update
-
WORK COMPLETED FOR WEEK ENDING 11/08/2025:
- Removed diaphragm formwork
- Continued work on bridge deck formwork
- Continued surcharge settlement period
-
WORK IN PROGRESS NEXT WEEK (11/09/2025 - 11/08/2025):
- Begin bridge deck rebar installation
- Continued work on bridge deck formwork
-
UPCOMING WORK THROUGH 11/30/2025:
- Work will continue on new bridge substructure and bridge deck.
- Surcharge settlement period will be 3 months