10/31/2025 Construction Update
-
WORK COMPLETED FOR WEEK ENDING 11/01/2025:
- Poured bridge diaphragms
- Worked on temporary walls and permanent walls at bridge approaches
- Completed surcharge placement
-
WORK IN PROGRESS NEXT WEEK (11/02/2025 - 11/08/2025):
- Remove diaphragm formwork
- Begin work on bridge deck formwork
-
UPCOMING WORK THROUGH 11/30/2025:
- Work will continue on new bridge substructure and bridge deck.
- Surcharge settlement period will be 3 months