10/03/2025 Construction Update
-
WORK COMPLETED FOR WEEK ENDING 10/04/2025:
- Complete pier caps and back walls
- Completed girder grout pads
-
WORK IN PROGRESS NEXT WEEK (10/05/2025 - 10/11/2025):
- Girder delivery and placement for spans 1 & 2
- Install temporary bag retaining wall and build up bridge approaches
- Continue levee work
-
UPCOMING WORK THROUGH 10/31/2025:
- Girder delivery and installation will be on the nights of 10/09/25 & 10/10/25. There will be a full closure of Stewart road during this time. The closure will be on the night of 10/09/25 from 8pm to 5am and the night of 10/10/25 from 8pm to 6am. Detour routes will be provided. Please see overview map of detour route below.