10/03/2025 Construction Update

  • WORK COMPLETED FOR WEEK ENDING 10/04/2025:

    • Complete pier caps and back walls
    • Completed girder grout pads
  • WORK IN PROGRESS NEXT WEEK (10/05/2025 - 10/11/2025):

    • Girder delivery and placement for spans 1 & 2
    • Install temporary bag retaining wall and build up bridge approaches
    • Continue levee work
  • UPCOMING WORK THROUGH 10/31/2025:

    • Girder delivery and installation will be on the nights of 10/09/25 & 10/10/25. There will be a full closure of Stewart road during this time. The closure will be on the night of 10/09/25 from 8pm to 5am and the night of 10/10/25 from 8pm to 6am. Detour routes will be provided. Please see overview map of detour route below.