09/26/2025 Construction Update
-
WORK COMPLETED FOR WEEK ENDING 09/27/2025:
- Complete pier caps and back walls
- Started levee work
- Removed all northern access from the river
- Started work on bag wall
-
WORK IN PROGRESS NEXT WEEK (09/28/2025 - 10/04/2025):
- Complete levee work
- Complete girder grout pads
- Install temporary bag retaining wall and build up bridge approaches
-
UPCOMING WORK THROUGH 10/31/2025:
- Girder delivery and installation will be on the nights of 10/09/25 & 10/10/25. There will be a full closure of Stewart road during this time. The closure will be from 8pm to 6am both nights. Detour routes will be provided.
- Brief traffic interruptions will occur during crane operations. Traffic impacts expected to be minimal.


