09/26/2025 Construction Update

  • WORK COMPLETED FOR WEEK ENDING 09/27/2025:

    • Complete pier caps and back walls
    • Started levee work
    • Removed all northern access from the river
    • Started work on bag wall
  • WORK IN PROGRESS NEXT WEEK (09/28/2025 - 10/04/2025):

    • Complete levee work
    • Complete girder grout pads
    • Install temporary bag retaining wall and build up bridge approaches
  • UPCOMING WORK THROUGH 10/31/2025:

    • Girder delivery and installation will be on the nights of 10/09/25 & 10/10/25. There will be a full closure of Stewart road during this time. The closure will be from 8pm to 6am both nights. Detour routes will be provided.
    • Brief traffic interruptions will occur during crane operations. Traffic impacts expected to be minimal.


Pier 3 Cap Formwork

Pier 3 Cap and back wall