09/04/2026 Construction Update

WORK COMPLETED FOR WEEK ENDING 09/05/2026:

  • Placed concrete for pier 2
  • Excavated and installed rebar cage for pier 3
  • Placed concrete for pier 3

WORK IN PROGRESS NEXT WEEK (09/06/2026 - 09/12/2026):

  • Complete pier 1 excavation
  • Place rebar cage for pier 1
  • Place concrete for pier 1

UPCOMING WORK THROUGH 09/30/2026:

  • In-water work window


Looking down into pier 2 shaft

Installing rebar cage for pier 3