WORK COMPLETED FOR WEEK ENDING 09/05/2026:
- Placed concrete for pier 2
- Excavated and installed rebar cage for pier 3
- Placed concrete for pier 3
WORK IN PROGRESS NEXT WEEK (09/06/2026 - 09/12/2026):
- Complete pier 1 excavation
- Place rebar cage for pier 1
- Place concrete for pier 1
UPCOMING WORK THROUGH 09/30/2026:
- In-water work window