08/21/2026 Construction Update

WORK COMPLETED FOR WEEK ENDING 08/22/2026:

  • Began excavation of Pier 2
  • Completed installation of stage 1 trestle finger access
  • Completed tying rebar for shaft 2

WORK IN PROGRESS NEXT WEEK (08/23/2026 - 08/29/2026):

  • Complete pier 2 excavation
  • Tie rebar for shaft 3
  • Continue removing sheet pile

UPCOMING WORK THROUGH 09/30/2026:

  • In-water work window


Installing Trestle Finger


Tying Pier 2 Shaft Rebar cage