08/21/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 08/22/2026:
- Began excavation of Pier 2
- Completed installation of stage 1 trestle finger access
- Completed tying rebar for shaft 2
WORK IN PROGRESS NEXT WEEK (08/23/2026 - 08/29/2026):
- Complete pier 2 excavation
- Tie rebar for shaft 3
- Continue removing sheet pile
UPCOMING WORK THROUGH 09/30/2026:
- In-water work window
Installing Trestle Finger
Tying Pier 2 Shaft Rebar cage