08/15/2025 Construction Update

  • WORK COMPLETED FOR WEEK ENDING 08/16/2025:

    • Complete driving 36" pile for southern trestle access
    • Complete driving sheet pile at northern trestle access
    • Install reaction frame for drilling permanent bridge shafts at pier 3
    • Excavated pier 1 shaft
    • Install shaft 1 rebar
  • WORK IN PROGRESS NEXT WEEK (08/17/2025 - 08/23/2025):

    • Complete testing of constructed pier 2
    • Remove Reaction Frame and Northern Access
    • Install Pier 3 cap formwork and pour
    • Pour pier 1 shaft
  • UPCOMING WORK THROUGH 09/30/2025:

    • In-water work will commence until end of fish window.
    • Brief traffic interruptions will occur during crane operations. Traffic impacts expected to be minimal.

Installing Shaft 2 Casing

Driving Steel Pile at Southern Trestle

#<Object:0x000000004a2d8e68>