08/14/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 08/15/2026:
- Completed installation of stage 1 reaction frame pile for pier 2
- Completed installation of stage 1 trestle finger pile
WORK IN PROGRESS NEXT WEEK (08/16/2026 - 08/22/2026):
- Complete driving pile
- Weld pile caps
- Install stringers at the trestle finger and reaction frame
UPCOMING WORK THROUGH 09/30/2026:
- In-water work window
Driving reaction frame pile
Driving Trestle Finger Pile