08/14/2026 Construction Update

WORK COMPLETED FOR WEEK ENDING 08/15/2026:

  • Completed installation of stage 1 reaction frame pile for pier 2
  • Completed installation of stage 1 trestle finger pile

WORK IN PROGRESS NEXT WEEK (08/16/2026 - 08/22/2026):

  • Complete driving pile
  • Weld pile caps
  • Install stringers at the trestle finger and reaction frame

UPCOMING WORK THROUGH 09/30/2026:

  • In-water work window


Driving reaction frame pile