08/08/2025 Construction Update
-
WORK COMPLETED FOR WEEK ENDING 08/08/2025:
- Complete testing of constructed pier 1
- Installed temporary casing for pier 2
- Excavated pier 2 shaft
- Install shaft 2 rebar
-
WORK IN PROGRESS NEXT WEEK (08/10/2025 - 08/16/2025):
- Continue driving 36" pile for southern trestle access
- Continue driving sheet pile at northern trestle access
- Install reaction frame for drilling permanent bridge shafts at pier 3
- Begin drilling pier 3 shaft
-
UPCOMING WORK THROUGH 09/30/2025:
- In-water work will commence until end of fish window.
- Brief traffic interruptions will occur during crane operations. Traffic impacts expected to be minimal.
Lowering rebar cage into shaft for pier 2

