08/07/2026 Construction Update

WORK COMPLETED FOR WEEK ENDING 08/08/2026:

  • Completed demolition of coffer cells
  • Removed existing piers 2 and 3
  • Flooded cells and began removing sheet pile
  • Began installation of reaction frame for pier 2

WORK IN PROGRESS NEXT WEEK (08/09/2026 - 08/15/2026):

  • Complete reaction frame for pier 2
  • Install work finger to access reaction frame

UPCOMING WORK THROUGH 09/30/2026:

  • In-water work window


Removing Existing Pier 2

Driving Reaction Frame Pile