08/07/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 08/08/2026:
- Completed demolition of coffer cells
- Removed existing piers 2 and 3
- Flooded cells and began removing sheet pile
- Began installation of reaction frame for pier 2
WORK IN PROGRESS NEXT WEEK (08/09/2026 - 08/15/2026):
- Complete reaction frame for pier 2
- Install work finger to access reaction frame
UPCOMING WORK THROUGH 09/30/2026:
- In-water work window
Removing Existing Pier 2
Driving Reaction Frame Pile