07/24/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 07/25/2026:
- Completed coffer cell for existing pier 2
- Excavated existing pier 2 coffer cell
- Started installation of coffer cell for existing pier 3
WORK IN PROGRESS NEXT WEEK (07/26/2026 - 08/01/2026):
- Remove existing pier 2
- Complete existing pier 3 coffer cell
- Remove existing pier 3
- Remove existing pier 2 coffer cell
UPCOMING WORK THROUGH 09/30/2026:
- In-water work window
Installing Existing Pier 2 Coffer Cell
Installing Existing Pier 3 Coffer Cell Template