07/24/2026 Construction Update

WORK COMPLETED FOR WEEK ENDING 07/25/2026:

  • Completed coffer cell for existing pier 2
  • Excavated existing pier 2 coffer cell
  • Started installation of coffer cell for existing pier 3

WORK IN PROGRESS NEXT WEEK (07/26/2026 - 08/01/2026):

  • Remove existing pier 2
  • Complete existing pier 3 coffer cell
  • Remove existing pier 3
  • Remove existing pier 2 coffer cell

UPCOMING WORK THROUGH 09/30/2026:

  • In-water work window


Installing Existing Pier 2 Coffer Cell


Installing Existing Pier 3 Coffer Cell Template