06/12/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 06/13/2026:
- Completed sheet pile cell
- Completed reaction frame
- Completed core fill at Pier 3
WORK IN PROGRESS NEXT WEEK (06/14/2026 - 06/20/2026):
- Prepare for shaft installation
UPCOMING WORK THROUGH 06/30/2026:
- Prepare site for in-water work for upcoming July fish window