WORK COMPLETED FOR WEEK ENDING 06/06/2026:

  • Completed sheet pile cell
  • Install reaction frame pile
  • Installed core fill at Pier 3

WORK IN PROGRESS NEXT WEEK (06/07/2026 - 06/13/2026):

  • Proof reaction frame
  • Backfill sheet pile cell and prepare for shaft installation

UPCOMING WORK THROUGH 06/30/2026:

  • Prepare site for in-water work for upcoming July fish window


Driving Reaction Frame Pile