06/05/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 06/06/2026:
- Completed sheet pile cell
- Install reaction frame pile
- Installed core fill at Pier 3
WORK IN PROGRESS NEXT WEEK (06/07/2026 - 06/13/2026):
- Proof reaction frame
- Backfill sheet pile cell and prepare for shaft installation
UPCOMING WORK THROUGH 06/30/2026:
- Prepare site for in-water work for upcoming July fish window