05/29/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 05/30/2026:
- Complete driving pile sheets
- Completed topsoil placement at NE corner of the site
WORK IN PROGRESS NEXT WEEK (05/31/2026 - 06/06/2026):
- Prepare site for reaction frame installation
- Install core fill at Pier 3
UPCOMING WORK THROUGH 06/30/2026:
- Prepare site for in-water work for upcoming July fish window
Driving Sheet Piles at West Abutment
Excavating Sheet Pile Cell