05/29/2026 Construction Update

WORK COMPLETED FOR WEEK ENDING 05/30/2026:

  • Complete driving pile sheets
  • Completed topsoil placement at NE corner of the site

WORK IN PROGRESS NEXT WEEK (05/31/2026 - 06/06/2026):

  • Prepare site for reaction frame installation
  • Install core fill at Pier 3

UPCOMING WORK THROUGH 06/30/2026:

  • Prepare site for in-water work for upcoming July fish window



Driving Sheet Piles at West Abutment


Excavating Sheet Pile Cell