04/03/2026 Construction Update

WORK COMPLETED FOR WEEK ENDING 04/04/2026:

  • Completed CSBC placement
  • Completed joint utility trench
  • Placed HMA pavement on east and west approach slabs
  • Installed temporary traffic barrier
  • Traffic will switch over on to the new bridge between 11:30pm Friday, April 4th and 1 AM Saturday, April 5th.

WORK IN PROGRESS NEXT WEEK (04/05/2026 - 04/11/2026):

  • Begin demo work on old bridge

UPCOMING WORK THROUGH 04/30/2026:

  • Begin demo of old bridge.
  • Utility work