04/03/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 04/04/2026:
- Completed CSBC placement
- Completed joint utility trench
- Placed HMA pavement on east and west approach slabs
- Installed temporary traffic barrier
- Traffic will switch over on to the new bridge between 11:30pm Friday, April 4th and 1 AM Saturday, April 5th.
WORK IN PROGRESS NEXT WEEK (04/05/2026 - 04/11/2026):
- Begin demo work on old bridge
UPCOMING WORK THROUGH 04/30/2026:
- Begin demo of old bridge.
- Utility work
Placing HMA Pavement on East Ramp
Removing Roadway at Butte Avenue for Grade Tie-in to West Approach Ramp