03/27/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 03/28/2026:
- Install CSBC at approaches
- Prepped for roadway paving
- Butte Avenue closing at Stewart Road from Saturday 3/28 to Monday 3/30
WORK IN PROGRESS NEXT WEEK (03/29/2026 - 04/04/2026):
- Continue work on approach ramps
- Butte Avenue closing at Stewart Road from Saturday 3/28 to Monday 3/30
- Traffic will switch on to the new bridge section on April 4th
UPCOMING WORK THROUGH 04/30/2026:
- Begin demo of old bridge.
- Utility work
- Work on east and west approach ramps
- Traffic will switch on to the new bridge section on the first week of April
Install CSBC on approach slab
Roadway tining of the new bridge deck