03/20/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 03/21/2026:
- Completed bridge deck tining
- Completed final waterline tie-in
- Prepped for roadway paving
- Completed joint utility trench tie-ins
WORK IN PROGRESS NEXT WEEK (03/22/2026 - 03/28/2026):
- Continue work on approach ramps
- Complete subgrade for roadway paving
UPCOMING WORK THROUGH 03/31/2026:
- Work will continue on new bridge substructure and bridge deck.
- Utility work
- Work on east and west approach ramps
- Traffic will switch on to the new bridge section on the first week of April