03/13/2026 Construction Update

WORK COMPLETED FOR WEEK ENDING 03/14/2026:

  • Completed north concrete pedestrian barrier
  • Pressure and purity tested new waterline
  • Prepped for roadway paving

WORK IN PROGRESS NEXT WEEK (03/15/2026 - 03/21/2026):

  • Complete joint utility trench
  • Continue work on approach ramps
  • Complete water utility tie-ins
  • Complete subgrade for roadway paving

UPCOMING WORK THROUGH 03/31/2026:

  • Work will continue on new bridge substructure and bridge deck.
  • Utility work
  • Work on east and west approach ramps
  • Traffic will switch on to the new bridge section on the first week of April


Installing North Pedestrian Barrier

Installing North Pedestrian Barrier

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>