03/13/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 03/14/2026:
- Completed north concrete pedestrian barrier
- Pressure and purity tested new waterline
- Prepped for roadway paving
WORK IN PROGRESS NEXT WEEK (03/15/2026 - 03/21/2026):
- Complete joint utility trench
- Continue work on approach ramps
- Complete water utility tie-ins
- Complete subgrade for roadway paving
UPCOMING WORK THROUGH 03/31/2026:
- Work will continue on new bridge substructure and bridge deck.
- Utility work
- Work on east and west approach ramps
- Traffic will switch on to the new bridge section on the first week of April