03/06/2026 Construction Update

WORK COMPLETED FOR WEEK ENDING 03/07/2026:

  • Continued utility installation
  • Completed installation of illumination conduit
  • Installed and weld expansion joint at east approach

WORK IN PROGRESS NEXT WEEK (03/08/2026 - 03/15/2026):

  • Place north pedestrian barrier
  • Continue work on approach ramps
  • Complete water utility installation under the bridge
  • Prep for roadway paving

UPCOMING WORK THROUGH 03/31/2026:

  • Work will continue on new bridge substructure and bridge deck.
  • Utility work
  • Work on east and west approach ramps


Placing Roadway Subgrade at West Approach


Installing Illumination Conduit