03/06/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 03/07/2026:
- Continued utility installation
- Completed installation of illumination conduit
- Installed and weld expansion joint at east approach
WORK IN PROGRESS NEXT WEEK (03/08/2026 - 03/15/2026):
- Place north pedestrian barrier
- Continue work on approach ramps
- Complete water utility installation under the bridge
- Prep for roadway paving
UPCOMING WORK THROUGH 03/31/2026:
- Work will continue on new bridge substructure and bridge deck.
- Utility work
- Work on east and west approach ramps
Placing Roadway Subgrade at West Approach
Installing Illumination Conduit