02/20/2026 Construction Update
WORK COMPLETED FOR WEEK ENDING 02/21/2026:
- Continued utility installation under the bridge
- Poured concrete east approach ramp
WORK IN PROGRESS NEXT WEEK (02/22/2026 - 02/28/2026):
- Continue installation of illumination conduit
- Continue work on approach ramps
- Continue water utility installation under the bridge
UPCOMING WORK THROUGH 02/28/2026:
- Work will continue on new bridge substructure and bridge deck.
- Utility work
- Work on east and west approach ramps
Joint Utility Trench Coming out of Bridge Substructure
Water Line comin gout of Bridge Substructure