01/30/2025 Construction Update

WORK COMPLETED FOR WEEK ENDING 01/31/2026:

  • Continued utility installation under the bridge
  • Continued surcharge material removal
  • Continued approach ramp work

WORK IN PROGRESS NEXT WEEK (02/01/2026 - 02/07/2026):

  • Complete surcharge material removal
  • Pour concrete approach ramps
  • Continued utility installation under the bridge

UPCOMING WORK THROUGH 02/28/2026:

  • Work will continue on new bridge substructure and bridge deck.
  • Utility work
  • Work on east and west approach ramps


Surcharge Material Removal at West Approach Ramp