01/23/2025 Construction Update

WORK COMPLETED FOR WEEK ENDING 01/24/2026:

  • Concrete bridge deck was fully poured
  • Surcharge period ended
  • Completed water line tie-ins on east side of bridge

WORK IN PROGRESS NEXT WEEK (01/25/2026 - 01/31/2026):

  • Begin to remove surcharge materials
  • Begin work on approach ramps
  • Install utilities under the bridge

UPCOMING WORK THROUGH 02/28/2026:

  • Work will continue on new bridge substructure and bridge deck.
  • Remove surcharge materials
  • Work on east and west approach ramps


Completed Phase 1 Concrete Bridge Deck Closure Segment

Finished and Curing Concrete Bridge Deck