March 23 → June 23 2020

Playground closed for removal of old equipment and preparing site for new equipment

June 24 → July 15 2020

Playground equipment delivery and installation

July 16 → August 05 2020

Prepare site, install poured in place surfacing and curing time

August 10 2020

Goal date for grand opening of inclusive playground

March 16 → March 16 2020

Council Approves Loyalty Park Inclusive Playground Equipment