March 23 → May 30 2020

Playground closed for removal of old equipment and preparing site for new equipment

June 02 → June 19 2020

Playground equipment delivery and installation

June 20 → June 27 2020

Prepare site, install poured in place surfacing and curing time

June 30 2020

Goal date for grand opening of inclusive playground

March 16 → March 16 2020

Council Approves Loyalty Park Inclusive Playground Equipment