March 16 → March 16 2020
Council Approves Loyalty Park Inclusive Playground Equipment
March 23 → June 23 2020
Playground closed for removal of old equipment and preparing site for new equipment
June 24 → July 15 2020
Playground equipment delivery and installation
July 15 → October 22 2020
Prepare site, install poured in place surfacing and curing time
October 23 → November 23 2020
Final phase
November 24 2020
Inclusive Playground open for everyone to enjoy!